Road Closings

ODOT works with its contactors to reduce the size of work zones and open as many lanes as possible through Memorial Day weekend. Current road closures will remain closed until their estimated completion date. All work will resume Tuesday, May 28.

ASHLAND COUNTY — The following construction projects are anticipated to affect highways in Ashland County next week. All outlined work is weather permitting and is subject to change.


U.S. Route 42 & State Route 302 intersection improvement – The U.S. 42 and State Route 302 intersection will be converted from the current two-way stop-controlled intersection into a single lane roundabout.

CONTINUING IMPACTS: Current Phase 1 Construction

  • SR 302 eastbound direction, from U.S. 42 to Township Rd 251/1080 intersection, remains closed for construction on the new roundabout. The intersection at U.S. 42 and SR 302 remains open, so motorists are able to travel along U.S. 42 during this phase of construction.
  • Access along SR 302 will be maintained for residents only. All residents and emergency personnel will need to enter the zone from SR 302 westbound.
  • Phase 1 work will approximately last from April 2024 till August 2024.
  • The detour route for all other motorists will be SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.

Estimated completion of entire project: October 2024


State Route 89 & State Route 302 intersection improvement – The State Route 89 and State Route 302 intersection will be converted from the current two-way stop-controlled intersection into a single lane roundabout.

NEW IMPACTS: Upcoming Phase 2 Construction

  • The SR 89 and SR 302 intersection will close Monday, June 3 for 60 days to construct the remaining roundabout at this intersection. Detour routes:
    • Local detour: SR 89 north to U.S. 42 east to SR 301 north to U.S. 224 west to SR 58 south to SR 89, and reverse.
    • All other motorists: SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.
  • Estimated completion of Phase 2: Friday, August 2, 2024
  • This is phase two of the project and will approximately last from June 2024 till August 2024.

CONTINUING IMPACTS: Current Phase 1 Construction

  • SR 302 eastbound direction, from SR 89 to U.S. 42 intersection, remains closed to traffic. The intersection at SR 89 and SR 302 remains open until Monday, June 3, so motorists are able to travel along SR 89 during this phase of construction.
  • Access along SR 302 will be maintained for residents only. All residents and emergency personnel will need to enter the zone from SR 302 westbound.
  • Phase 1 work will approximately last from April 2024 till June 2024.

Estimated completion of entire project: October 2024

Click here for additional information about ongoing projects in the county.